Most of our websites take 8 to 14 weeks from the first conversation to launch. Here’s where that time goes, and how to keep your project at the quicker end.
The short answer
| Stage | Typical time |
|---|---|
| 1. Discovery and planning | 1–2 weeks |
| 2. Wireframes and design | 2–4 weeks |
| 3. Content (alongside design) | 2–4 weeks |
| 4. Development | 4–6 weeks |
| 5. Testing and review | 1–2 weeks |
| 6. Launch and training | 1 week |
| 7. Care after launch | Ongoing |
| Total | 8–14 weeks |
What happens at each stage
1. Discovery and planning (1–2 weeks)
We start with why your business exists, who the website is for and what you want visitors to do. That becomes a short brief and a sitemap everyone agrees on.
2. Wireframes and design (2–4 weeks)
We plan each page’s structure first, then design how it looks: colour, type, imagery and the details that make it yours. You see designs before anything is built.
3. Content (2–4 weeks, alongside design)
Words, photos and video. This is the stage that most often holds projects up, so we start it early and can help with copywriting and photography.
4. Development (4–6 weeks)
We build the approved designs in WordPress, add features like forms, booking or shops, and make sure everything works on every screen size.
5. Testing and review (1–2 weeks)
We check browsers, devices, speed, accessibility and security, and you review the site before it goes live.
6. Launch and training (1 week)
We put the site live and show you how to update it yourself.
7. Care after launch (ongoing)
Updates, backups, security and small changes, through one of our care plans. See our website care plans
What makes a website take longer?
- Content arriving late. It’s the most common delay by far.
- Lots of people signing off. Agree early who gives feedback and who has the final say.
- Extra features, such as online shops, booking systems or links to other software.
- Changing the brief halfway through.
How to keep your project on track
- Gather your content early, or let us help write it.
- Name one person to collect feedback.
- Give feedback within a few days of each stage.
- Keep “nice to haves” for after launch.
FAQs
Can a website be built in less than 8 weeks?
Sometimes. A smaller site with content ready to go can be quicker. We’ll tell you honestly on a discovery call.
Does a new brand add time?
Yes, usually 6 to 10 weeks before website design starts. Doing both together is still faster than one after the other. How much does branding cost?
How much does it cost?
See our guide: How much does a website cost?
Got a launch date in mind? Book a free 30-minute discovery call and we’ll tell you whether it’s realistic, and what it would take.